Sr.No Description of Works Plant / Client Name Duration Status
1. Composite Electrical works in upcoming  Oil Refinery including Erection, Testing & commissioning of Transformers, LT/ HT Bus bars, HT/LT Motors, Laying HT/LT Cables & installation of C&I system at Dangote Refinery Nigeria. Dangote Refinery 18 Months Continue…
2. Assembly Erection, Testing & Commissioning of H&M Equipment’s for Kano Hydro Electric Project for Skipper Nigeria Limited, at Tiga Site, Nigeria Skipper Nigeria Limited 8 Months Continue…
3. Mechanical Field Works at IIR Butyl Rubber Plant-, Structural Steel Fabrication & Erection, Equipment Erection (Static & Rotary), ABG Piping, Bolt Torqueing etc… Reliance Sibur Elastomers Private Limited 12 Months Continue…
4.  

Under Ground Piping Works

Reliance Sibur Elastomers Private Limited 8 Months Continue…
5. Mechanical Maintenance of rotary parts on round the clock basis for PNC at IOCL (Refineries Division) Panipat Naphtha Cracker, Panipat, Haryana. IOCL 12 Months Continue…
6. Structural, Piping and Equipment(Static & Rotary) Installation Works 5000 MT at Reliance Industries, Jamnagar, SEZ 1 and SEZ 2 Steam Supper Heater Project Reliance/ Linde Engineering India Ltd 09 Months Completed
7. Piping & Structural Steel works of Mechanical Contract for Additive Dosing tank In DTA RTF.(30000 IND) Reliance Jamnagar Refinery 06 Months Completed
8. Stack Height Increase, CFN Piping and Flue Gas

Duct jobs at SEZ-FCCU Reliance Industries Limited Jamnagar Gujarat.

Reliance Jamnagar Refinery 2.5 Month Completed
9. IBR Related Piping Modification/ Inspection Jobs at SEZ-FCCU Area Reliance Industries Limited Jamnagar Gujarat. Reliance Jamnagar Refinery 1.5 Month Completed
10.  Fabrication, Erection, Testing and Commissioning of Piping along with Rotating Equipment’s includes CS,AS,SS,P91, 904L, LTCS, Rubber Line, Jacketed piping, Cast Iron (5,10,000 Inch Meter) of 2 Million Tonne Capacity Di Ammonia Phosphate Fertilizer Plant at OCFL Paradeep Orissa OCFL 24 Months Completed
11. Fabrication, Erection, Testing and commission of piping (Executed Qty: – 74000 INM which includes P-91, P-11, 22, SS- 304L, 316L, 310 L,CS)  of combined cycle of 72 MW including commissioning of HRSG, GTG and STG  at OMPL (Petrochemical Complex)  at Mangalore, Karnataka. OMPL/TOYO/ THERMAX 12 Months Completed
12. Erection, testing & commissioning of complete sulphur furnace package with burners, Boiler drum, furnaces, IBR & NIBR piping at IOCL, Panipat Refinery.

 

IOCL/ISGEC 06

Months

Completed
13. Structural Steel Fabrication/ Mechanical and other related Works at SFS- SEZ, RIL- Jamnagar J3 Project Reliance Jamnagar Refinery 30 Months Completed
14. Structural Erection works-MEG area

 

Reliance Jamnagar 08 Months Completed
15. Mechanical structural erection at SEZ PCG area Reliance Jamnagar 01 Year Completed
16. Circular Platform Erection works SEZ-MEG area Reliance Jamnagar 02 Months Completed
17. Turn around Maintenance of SAP & PAP at 01 MT capacity at ICS-Senegal (International). Includes Piping, Equipment’s(rotary +Static) ICS Senegal 06 Months Completed
18. Assembly and Erection of steel stack along with Platforms of 74 Mtrs height of 72MW at OMPL, Mangalore, Karnataka (QTY -02 No. stacks). OMPL/TOYO/ THERMAX 03 Months Completed
19.  Assembly, Erection, Testing and Commissioning of Static and Rotating Equipments(Total Weight 19000 MT) of 02 Million Tonne Capacity Di Ammonia Phosphate Fertilizer Plant at OCFL, Paradeep, Orissa OCFL 22 Months Completed
20. Fabrication of Pressure Vessels and Evaporators.

 

Y’NAGAR/ ISGEC 1.5 Years Completed
21. Fabrication, Assembly, Welding, Pre/Post Weld Treatment and Hydro Testing of Headers.

 

Y’NAGAR/ ISGEC 36 Months Completed
22. Design, Detailing, Supply of Material, Fabrication, Erection and Assembly of Access & Platforms at 4×600 MW IPP of Sterlite Energy limited at Jharsuguda, Orissa. SEL IPP/ EESI 12 Months Completed
23. Fabrication of Pressure Parts of High Pressure Boiler Components i.e. Water Wall Tubes, Economiser, LTSH, Loose Tubes, Panels, Roof Tubes. RATANGARH/ ISGEC 2.5 Years Completed
24. Fabrication of the secondary structures, Duct, Elevators and Miscellaneous Platforms for 2 x 700 MW Boilers. LNT-MHI/ FL 12 Months Completed
25. Fabrication of structures, ducting, Boiler Elevators at 2×600 MW at Reliance 2×600 MW Hisar, Haryana.

 

HPGCL/

Reliance

12 Months Completed
26. Erection & Commissioning of Mechanical Works For Boiler, ESP, IBR/NIBR Piping and BOP &UNLOADING, STACKING VERIFICATION,STORE MANAGEMENT For 1X20 MW MWV India Packaging Board PVT Ltd Vapi, Gujarat Thermax/ Vapi 12 Months Completed
27. Mechanical Erection Work of Boiler, ESP, Piping & auxiliaries including Housekeeping and Material Handling for 1×4.1 MW CPP of NV International Pvt. Ltd. NV International/Thermax 12 Months Completed
28. Erection, Testing and Commissioning of complete package of ESP, Milling System, Fans and Ducting of 2 x 250 MW Power Plant at GHTP, Lehra Mohabat , PSEB, Bathinda Punjab PSEB 24 Months Completed
29. Complete Erection, Testing, Trail Assembly, Commissioning of Sky Climber of 2 x 600 MW Power Plant at RGTPP, Hisar Haryana HPGCL/REL 02 Months Completed
30. Assistance in Operations, Commissioning & Stabilization of 2 x 600 MW Boiler, Turbine, BOP, Electrical and C&I at RGTP, Hisar RGTPP/REL 12 Months Completed
31. Assistance in Operations, Commissioning & Stabilization of 2 x 300 MW Boiler, Turbine, BOP, Electrical, C&I at DCRTPS Y’Nagar DCRTPS/REL 12 Months Completed
32. Erection, Testing & Commissioning of 1×170 TPH CFBC Boiler, IBR Piping, Fans, Ducting, APH etc. at Rewa. JAYPEE 18 Months Completed
33. Erection & Alignment of Structure of lift for Unit – 1 including Sheeting of 2×600 MW at RGTPP, Hisar

 

 

RGTPP/REL 05 Months Completed
34. Erection, Testing & Commissioning of 12 MW Travelling Grate Boiler with IBR Piping, Cooling Water Piping, Raw Water Piping, DM Water Piping, ESP, Fans, APH, Ducting etc. PBPL/ PBPL 16 Months Completed
35. Erection of the Balance Structure and Piping (IBR& NIBR) work for Unit – 1 & 2 of 2 x 600 MW. RGTPP/

HISSAR

08 Months Completed
 

36.

 

Modification of the Structure including addition of Landing Platform at different level for Unit – 1 & 2 of 2 x 600 MW

 

RGTPP/

HISAR

 

06 Months

 

Completed

37. Complete Work of Dust Suppression System of 4 x 110MW and 2 x 250 MW work including Civil Works, Erection & Commissioning of Pumps which also includes laying Underground Piping with Wrapping and Coating & Commissioning of complete DSS at Panipat HPGCL/WRC 12 Months Completed
38. Erection, Testing and Commissioning and Allied Works (Including Housekeeping and Material Management) along with Power Cycle and Utility for 10 MW Waste Heat Recovery CPP at JK Cement, Chitourgarh, Rajasthan JK Cement/

Thermax

12 Months Completed
39. Resolving Operation problems including proposing modifications of 4 x 135 MW, CFBC Boilers at DCPP, JSPL, Raigarh JSPL 01 Month Completed
40. Erection, Testing & Commissioning of 1×120 TPH Travelling Grate Boiler, IBR Piping, Fans, Ducting, APH at Khatauli in Uttar Pradesh TRIVENI/IJT 11 Months Completed
41. Erection, Testing & Commissioning of 1×47 TPH Travelling Grate Boiler, Ducting, APH, ESP, IBR Piping in Rajasthan SANJOG SUGARS/ IJT 06 Months Completed
42. Fabrication, Painting, Erection, Welding, Alignment  of Turbine with auxiliaries and Pipe Rack Structure of  Fuel handling system of 2 x 250 MW at Panipat HPGCL/ INDURE 08 Months Completed
43. Complete Package of Fuel Handling system with Piping IBR /NON IBR including Processed Piping with Pumps and Oil Tanks of HFO /LDO Tanks with Steam Heaters  of 2 x 250 MW at Panipat HPGCL/

Utility