STEAG/TSPL
STEAG/TSPL
Sr. No | Description of Works | Plant / Client Name | Duration | Status |
1 | Annual Mechanical Maintenance Contract for Boiler & its Auxiliaries, TG & its Auxiliaries, Balance of Plant, Operation Assistance in Water Treatment Plant including material handling and Housekeeping of 3x660MW Super Critical Power Plant of M/S Talwandi Sabo Power Limited,Vill. Banwala, Dist. Mansa, Punjab for Five Years.
|
STEAG/TSPL | 60 Months | Continue… |
2. |
Operation and maintenance of Boiler, Ash Handling & its Auxiliaries of 3×660 MW Super Critical Thermal Power Plant at Talwandi Sabo, Mansa Punjab.
|
TSPL/Vedanta Group |
36 Month |
Completed |
3. | Operation and maintenance of Boiler, Turbine generator including BOP of 165 MW combined cycle based power plant at HMEL, Bathinda (Punjab). | STEAG/HMEL | 24 Month | Completed |