| Sr. No |
Description of Works |
Plant / Client Name |
Duration |
Status |
| 1. |
Annual Overhaul activities of Boiler, Burner, Valve, Pressure Parts ,ESP, Mills, Ducts and Dampers, APH & Fans of SBU 2, 2×300 MW . |
JSW/Bellary |
09 Days |
Completed |
| 2. |
Annual Overhaul activities of Boiler, Burner, Valve, Pressure Parts ,ESP, Mills, Ducts and Dampers, APH & Fans of CPP3, 2×300 MW. |
JSW/Bellary |
45 Days |
Completed |
| 3. |
Annual Overhauling of Turbine, Boiler and its Auxiliaries, APH & Fans with auxiliaries at CPP 2 at JSW Energy, Bellary. |
JSW/Bellary |
01 Months |
Completed |