SKIPPER NIGERIA LIMITED
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Assembly Erection, Testing & Commissioning of H&M Equipment’s for Kano Hydro Electric Project for Skipper Nigeria Limited, at Tiga Site, Nigeria | Skipper Nigeria Limited | 08 Months | Continue… |
NPL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Commissioning Support for Mechanical Maintenance Work of Power Plant Equipment’s, Piping, Valves etc. at 2×700 MW NPL Rajpura, Punjab | NPL | 06 Months | Completed |
| 2. | Operation & Maintenance Services of Ash Handling Plant (AHP), Mill Reject System (MRS) and Recovery system WRS at 2X700 MW Nabha Power Limited.
|
L&T Nabha Power. | 12+24 Month | Continue… |
JSW/BELLARY
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Annual Overhaul activities of Boiler, Burner, Valve, Pressure Parts ,ESP, Mills, Ducts and Dampers, APH & Fans of SBU 2, 2×300 MW . | JSW/Bellary | 09 Days | Completed |
| 2. | Annual Overhaul activities of Boiler, Burner, Valve, Pressure Parts ,ESP, Mills, Ducts and Dampers, APH & Fans of CPP3, 2×300 MW. | JSW/Bellary | 45 Days | Completed |
| 3. | Annual Overhauling of Turbine, Boiler and its Auxiliaries, APH & Fans with auxiliaries at CPP 2 at JSW Energy, Bellary. | JSW/Bellary | 01 Months | Completed |
ACBIL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Annual Overhauling of Turbine & Auxiliaries of Unit 1 & 2 at 2x 135 MW, ACBIL, Kasaipali, Chhattisgarh. | ACBIL | 01 Months | Completed |
| 2. | Annual Contract for Operation & Maintenance of Boiler & its auxiliaries, Turbine auxiliaries, CHP, AHP, WTP and BOP at 2x50MW Spectrum Coal & power limited, Chhattisgarh. | ACB-Spectrum Coal & Power | 12+12 Months | Completed |
MCCPL,CG
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Inspection and correction of Turbine bearing no. 01 to 09, alignment of MOP & Bearing gear at 1x 300 MW MCCPL, Bandhakhar, and Chhattisgarh. | MCCPL, CG | 01 Months | Completed |
| 2. | Maintenance works for Electrical and Control & Instrumentation of 1×300 MW Thermal Power Plant. | Maruti Clean & Coal power Ltd | 12 Months | Completed |
TSPL, PUNJAB
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Annual Overhauling of Boiler Pressure Part, Esp Duct & Dampers, APH & Fans of Unit 1 of 3X660 MW, Talwandi Sabu Power Plant (TSPL), Mansa, Punjab. | TSPL, Punjab | 01 Months | Completed |
| 2. | Annual Overhauling of Boiler Pressure Part, Esp Duct & Dampers, APH & Fans of Unit 2 of 3X660 MW, Talwandi Sabu Power Plant (TSPL), Mansa, Punjab. | TSPL, Punjab | 01 Months | Completed |
| 3. | Annual Overhauling of Boiler Pressure Part, Esp Duct & Dampers, APH & Fans of Unit 2 of 3X660 MW, Talwandi Sabu Power Plant (TSPL), Mansa, Punjab. | TSPL, Punjab | 02 Months | Completed |
TATA POWER-CGPL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Annual Overhauling of Boiler & its auxiliaries of Unit #40 & Unit # 50 at Costal Gujarat Power Limited (TATA POWER-5X800 MW), Mundra | TATA POWER -CGPL | 06 Months | Continue… |
| 2. | Annual Overhauling of Boiler & its auxiliaries of Unit #40 at Costal Gujarat Power Limited (TATA POWER-5X800 MW), Mundra | TATA POWER -CGPL | 02 Months | Completed |
HPGCL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Complete Maintenance of Coal Mills, RC Feeders and PF Piping of 2×300 MW at Unit – 1&2. | DCRTPP/HPGCL | 15 Months | Completed |
| 2. | Complete Maintenance of Coal Mills, RC Feeders and PF Piping of 2×300 MW at Unit – 1&2. | DCRTPP/HPGCL | 15 Months | Completed |
| 3. | Complete Maintenance of Coal Mills, RC Feeders of 2 x 600 MW Boiler at Unit–1&2 at RGTPP/HISAR | HPGCL/ HISAR | 15 Months | Completed |
| 4. | Assistance in Operations, Commissioning & Stabilization of 2 x 600 MW Boiler, Turbine, BOP, Electrical and C&I at RGTP, Hisar | HPGCL/ HISAR | 12 Months | Completed |
| 5. | Erection & Alignment of Structure of lift for Unit – 1 including Sheeting of 2×600 MW at RGTPP, Hisar | HPGCL/ HISAR | 05 Months | Completed |
| 6. | Erection of the Balance Structure and Piping (IBR& NIBR) work for Unit – 1 & 2 of 2 x 600 MW at RGTPP, Hisar | HPGCL/ HISAR | 08 Months | Completed |
| 7. | Modification of the Structure including the addition of Landing Platform at a different level for Unit – 1 & 2 of 2 x 600 MW at RGTPP, Hisar | HPGCL/ HISAR | 06 Months | Completed |
| 8. | Replacement of Support/Guide Bearing of APH of 2 x 600 MW at Hisar. | HPGCL/HISAR | 01 Months | Completed |
| 9. | Fabrication of structures, ducting, Boiler Elevators at 2×600 MW at Reliance 2×600 MW Hisar, Haryana. | HPGCL/HISAR | 12 Months | Completed |
| 10. | Complete Erection, Testing, Trail Assembly, Commissioning of Sky Climber of 2 x 600 MW Power Plant at RGTPP, Hisar Haryana | HPGCL/HISAR | 02 Months | Completed |
| 11. | Complete Work of Dust Suppression System of 4 x 110MW and 2 x 250 MW work including Civil Works, Erection & Commissioning of Pumps which also includes laying Underground Piping with Wrapping and Coating & Commissioning of complete DSS. | HPGCL/HISAR | 12 Months | Completed |
| 12. | Fabrication, Painting, Erection, Welding, Alignment of Turbine with auxiliaries and Pipe Rack Structure of Fuel handling system of 2 x 250 MW at Panipat. | HPGCL/PANIPAT | 08 Months | Completed |
| 13. | Complete Package of Fuel Handling system with Piping IBR /NON-IBR including Processed Piping with Pumps and Oil Tanks of HFO /LDO Tanks with Steam Heaters of 2 x 250 MW at Panipat. | HPGCL/PANIPAT | 09 Months | Completed |
| 14. | Annual Overhauling of Pressure Parts of Boiler unit #1 and Unit #2 at 2×600 MW CLP Jhajjar- Haryana | CLP/JHAJJAR | 02 Months | Completed |
| 15. | Annual Overhauling of APH & Fans of unit #1 at 2×600 MW CLP Jhajjar- Haryana | CLP/JHAJJAR | 01 Months | Completed |
| 16. | Assistance in Operations, Commissioning & Stabilization of 2 x 300 MW Boiler, Turbine, BOP, Electrical, C&I at DCRTPS Y’Nagar | DCRTPS/REL | 12 Months | Completed |
PTPS/HPGCL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Maintenance of all Equipment’s of Conveyor System (Routine & Breakdown) & Heavy Equipment’s of Coal Handling Plant – II of 2 x 210 MW PTPS-HPGCL, Panipat Haryana | PTPS/HPGCL | 07 Months | Completed |
| 2. | Complete Mechanical Maintenance of Types of equipment of Conveyor System of Coal Handling Plant-I of 4 x 110 MW Boilers. |
PTPS/HPGCL |
24 Month |
Completed |
| 3. | Complete Mechanical Maintenance of Crusher, RDM, Wagon Tippler, Motors, and other Allied Equipment’s installed at CHP-II of 2 x210 MW PTPS-HPGCL, Panipat Haryana. | PTPS/HPGCL | 15 Month | Completed |
| 4. | Complete Maintenance of Tube Coal Mills, RC Feeders & Vibrators & miscellaneous Boiler Works of 210 MW Boiler at Unit – 6 | PTPS/HPGCL | 15 Month | Completed |
|
5. |
Complete Maintenance of Coal Mills, RC Feeders, PF Piping and O&M of Tramp Iron Gates of 2 x 110 MW at Unit – 1 & 2. | PTPS/HPGCL | 15 Month | Completed |
| 6. | Complete Maintenance of Coal Mills, RC Feeders & Variations & miscellaneous Boiler Works of 210 MW Boiler at Unit – 5 | PTPS/HPGCL | 15 Month | Completed |
| 7. | Complete Maintenance of Coal Mills, RC Feeders, PF Piping and O&M of Tramp Iron Gates of 2 x 110 MW at Unit 1 & 2. | PTPS/HPGCL | 15 Month | Completed |
| 8. | Routine/Breakdown/Capital Maintenance of all Electrical & Electronics (C&I) Equipment’s of Unit – 7&8 | PTPS/HPGCL | 15 Months | Completed |
| 9. | Routine/Breakdown/ Capital Maintenance of all Electrical & Electronics (C&I) Equipment of Unit 2×250 MW – 7&8 | PTPS/HPGCL | 15 Month | Completed |
| 10. | Routine/Breakdown/ Capital Maintenance of all Electrical &Electronics (C&I) Equipment of Unit –7&8 of 2×250 MW | PTPS/HPGCL | 15 Month | Completed |
| 11. | Routine/Breakdown/ Capital Maintenance of all Electrical & Electronics (C&I) Equipment of CHP-II of 2×210 MW Boilers | PTPS/HPGCL | 07 Month | Completed |
| 12. | Maintenance / Replacement of Fabric / Conveyor Belt Compensators over existing Metallic Expansion Joints of Boiler of 110 MW at Unit -2 | PTPS/HPGCL | 04 Month | Completed |
| 13. | Capital Overhauling of Pressure Parts (First pass & Second Pass ) of Unit # 5 of 210 MW capacity at PTPS, Panipat | PTPS/HPGCL | 01 Month | Completed |
| 14. | Capital Overhauling of Pressure Parts (First pass & Second Pass ) of Unit # 4 of 110 MW capacity at PTPS, Panipat | PTPS/HPGCL | 01 Months | Completed |
| 15. | Capital Overhauling of RAH, ESP, Dampers & Gates & Ducting of 210 MW Boiler at Unit-6 | PTPS/HPGCL | 01 Month | Completed |
| 16. | Overhauling of complete Pressure Parts, Pent House, APH of 110 MW Boiler at Unit-2 | PTPS/HPGCL | 01 Month | Completed |
| 17. | Overhauling of Pressure Parts, Cleaning, Washing & Repairing of the Pent House of 110 MW Boiler at Unit – 3 | PTPS/HPGCL | 01 Month | Completed |
|
18. |
Overhauling of RAH, ESP, Gates & Dampers, various Ducts of 210 MW Boiler at Unit-5 | PTPS/HPGCL | 01 Month | Completed |
| 19. | Repair/Rectification of 6 Nos. Damaged ESP Fields / ESP Structure along with Replacement of the Slide Bearing of 210 MW Boiler at Unit-6 | PTPS/HPGCL | 01 Month | Completed |
| 20. | Overhauling of Instrument Air Compressor of 110 MW Boiler at Unit-2 | PTPS/HPGCL | 01 Month | Completed |
| 21. | Operation and Maintenance of complete Coal Handling Plant – II of 2×210 MW, PTPS-HPGCL, Panipat Haryana | PTPS / TECPRO | 07 Month | Completed |
|
22. |
Operation & Maintenance of Routine/Breakdown/Capital Maintenance of all Electrical & Electronics (C&I) Equipment of Coal handling Plant – III of 2×250 MW, PTPS-HPGCL, Panipat Haryana. | PTPS / TECPRO | 07 Month | Completed |
| 23. | Renovation & Modernization of Conveyor Belts by replacing existing Toughing Idlers frame with Rollers, Flat Return Idlers, Toughing Training Idlers, Return Training Idlers & Impact Idlers of 20 Toughing Angle with 35 Toughing Angle Idlers & replacement of Vibrating Feeders, Flap Gates, Transfer Chutes of Coal Handling Plant – I of 4 x 110 MW, PTPS-HPGCL, Panipat Haryana. | PTPS/RMEC | 06 Months | Completed |
| 24. | Routine, Breakdown & Capital Maintenance of all Electrical & Electronics (C&I) Types of equipment in CHP-II of 2 x 210 MW Boilers. | PTPS/RMEC | 15 Months | Completed |
| 25. | Routine/Breakdown/ Capital Maintenance of all Electrical & Electronics (C&I) Equipment of Coal Handling Plant – III of 2×250 MW | PTPS/RMEC | 15 Months | Completed |
| 26. | Overhauling of RAH, ESP, Dampers & Gates & Ducting of 210 MW Boiler at Unit-6 | PTPS/RMEC | 01 Months | Completed |
| 27. | Complete Maintenance of Coal Mills, RC Feeders & Variations & miscellaneous Boiler Works of 210 MW Boiler at Unit – 5 | PTPS | 15 Months | Completed |
| 28. | Capital overhauling of unit-3 of 110Mw at PTPS Panipat complete pressure parts. | PTPS | 1.5 Month | Completed |
KEC International
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Operation & Maintenance of 1 X 18 MW solar Power Plant orf KEC International at Jalaun, Uttar Pradesh. | KEC International | 36 Months |
Completed |