TRN Energy Limited
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Maintenance Contract of BTG & Mill Reject System at 2X300 MW TRN Energy Private Limited, Vill-Bhengari, Po- Nawarpara(Tenda), Tehsil-Gharghoda, Raigarh (C.G.)
|
TRN Energy Limited | 36 Months | Continue… |
| 2. | Maintenance Work For Electrical and C & I at 2X300 MW TRN Energy Private Limited, Vill-Bhengari, Po-Nawarpara(Tenda), Tehsil-Gharghoda, Raigarh (C.G.)
|
TRN Energy Limited | 36 Month | Continue… |
| 3. | Annual Service Contract for Maintenance of Main Plant and Plant Water System at 2X300 MW TRN Energy Private Limited, Vill-Bhengari, Po-Nawarpara(Tenda), Tehsil-Gharghoda, Raigarh (C.G.)
|
TRN Energy Limited | 12 Month | Completed |
| 4. | Operation & Maintenance of Ash Handling Plant at 2 X 300 MW TRN Energy Pvt.Ltd, Vill-Bhengari, Po-Nawarpara(Tenda), Tehsil-Gharghoda, Raigarh (C.G.)
|
TRN Energy Limited | 12 Month | Completed |
STEAG/TSPL
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Annual Mechanical Maintenance Contract for Boiler & its Auxiliaries, TG & its Auxiliaries, Balance of Plant, Operation Assistance in Water Treatment Plant including material handling and Housekeeping of 3x660MW Super Critical Power Plant of M/S Talwandi Sabo Power Limited,Vill. Banwala, Dist. Mansa, Punjab for Five Years.
|
STEAG/TSPL | 60 Months | Continue… |
|
2. |
Operation and maintenance of Boiler, Ash Handling & its Auxiliaries of 3×660 MW Super Critical Thermal Power Plant at Talwandi Sabo, Mansa Punjab.
|
TSPL/Vedanta Group |
36 Month |
Completed |
| 3. | Operation and maintenance of Boiler, Turbine generator including BOP of 165 MW combined cycle based power plant at HMEL, Bathinda (Punjab). | STEAG/HMEL | 24 Month | Completed |
JSW
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Operation & Maintenance of Ash Handling Plant CPP Unit 3 & 4 (4X300 MW) at JSW Energy Limited, Bellary, Karnataka.
|
JSW | 36 Months | Continue… |
| 2. | Annual Maintenance, Preventive Maintenance & Breakdown Maintenance of Boiler, Turbine and its Auxiliaries CPP- I,II,III,IV & SBU- I,II at 1690 MW JSW Energy Limited, Bellary Karnataka.
|
JSW |
36 Month |
Continue… |
| 3. | AMC for Mechanical Preventive Maintenance & Misc. Services of Boiler and Auxiliaries of SBU 2 and CPP3&4 units Three Units (4X300 MW) at JSW Energy Limited, Bellary, Karnataka. | JSW | 24+12 Month | Completed |
| 4. | AMC for Mechanical Breakdown Maintenance & Misc. Services of Boiler, CHP and Auxiliaries of SUB2 and CPP3&4 Three Units (4X300 MW) at JSW Energy Limited, Bellary, Karnataka.
|
JSW | 24+12 Month | Completed |
|
5. |
Annual Overhauling of ESP, APH of SBU #2, CPP3 at 4X300 MW JSW Energy, Bellary
|
JSW | 02 Month | Completed |
| 6. | Annual Overhauling of Boiler and Turbine with auxiliaries at 4X300 MW JSW Energy, Bellary | JSW | 02 Month | Completed |
| 7. | Annual Overhauling of LT Motors at 4X300 MW JSW Energy, Bellary | JSW | 02 Month | Completed |
SEL IPP/ EESI
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Complete Maintenance (Routine, Breakdown, Preventive) of Boilers along with its auxiliaries of 4 x 600MW Boilers at Evonik Energy Service(India) Pvt. Limited Jharsuguda | SEL IPP/ EESI | 52 Months | Completed |
| 2. | Field Operations of BOP of 4 x 600 MW Boilers at Evonik Energy Service(India) Pvt. Limited Jharsuguda | SEL IPP/ EESI | 42 Month | Completed |
| 3. | Capital Overhauling of Pressure Parts, Burners, Pent & Dog House, Fans – (ID/FD/PA/SA), Valves, Ducting, Pumps, Compressors, Gates and Dampers etc. of 2 x 600 MW Power Plants at Jharsuguda. | SEL IPP/ EESI | 01 Months | Completed |
| 4. | Maintenance for the housekeeping and material management of 4 x 600 MW boilers at Evonik Energy Service(India) Pvt. Limited Jharsuguda | SEL IPP/ EESI | 36 Month | Completed |
| 5. | Capital Overhauling of ESP & Bag Filters of 2 x 600 MW Power Plants at Jharsuguda. | SEL IPP/ EESI | 01 Month | Completed |
| 6. | Capital Overhauling of Coal Mills, Gates & Dampers of 2 x 600 MW Power Plants at Jharsuguda. | SEL IPP/ EESI | 01 Month | Completed |
| 7. | Capital Overhauling of Air Pre Heaters of 2 x 600 MW Power Plants at Jharsuguda. | SEL IPP/ EESI | 01 Month | Completed |
| 8. | Design, Detailing, Supply of Material, Fabrication, Erection and Assembly of Access & Platforms at 4×600 MW IPP of Sterlite Energy limited at Jharsuguda, Orissa. | SEL IPP/ EESI | 12 Months | Completed |
DB POWER
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Commissioning Support for Complete Power Plant for Mechanical, Electrical and C&I for BTG, BOP Equipment, Associated Piping, CHP & AHP of 2×600 MW DBPL BADAHARA, Chhattisgarh | DB POWER | 24 Month | Completed |
Adani Power Rajasthan Ltd.
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Providing Complete mechanical maintenance Service including preventive maintenance, regular maintenance & break down maintenance of Boiler & its Auxiliaries (including ESP), Turbine Auxiliaries and BOP and Boiler tubes weld joints repair for Unit-I & II, Kawai Thermal Power Plant, Rajasthan
|
Adani Power Rajasthan Ltd. | 24 Month | Continue… |
NTPC Limited
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Triennial Maintenance (Running Maintenance, Breakdown Works) Contract of Boiler, Turbine, Air Compressors and AC of Stage-I (3 X 800 MW) Units at NTPC Kudgi, Karnataka
|
NTPC Limited, Kudgi | 36 Month | Continue… |
|
2. |
Triennial Maintenance (Running Maintenance, Breakdown Works) Contract of Balance of Plant (BOP) of Stage-I (2 X 800 MW) Units at NTPC Gadarwara
|
NTPC Limited |
36 Month |
Continue… |
Essar Power M.P Limited
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Annual Mechanical Maintenance of BTG, BOP and AHP for Unit # 1 & Unit # 2 | Essar Power M.P Limited | 36 Month | Continue… |
| 2. | Annual overhauling of Boiler Pressure Part, APH, FAN, Coal Burner, Safety valve 2X600 MW Essar Power M.P Limited, Bandhora, Waidhan, M.P
|
Essar Power M.P Limited | 1 Month | Completed |
ISGEC
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1. | Fabrication of Pressure Vessels and Evaporators. | Y’NAGAR/ ISGEC | 1..5 Years | Completed |
| 2. |
Fabrication, Assembly, Welding, Pre/Post Weld Treatment and Hydro Testing of Headers. | Y’NAGAR/ ISGEC |
36 Month |
Completed |
| 3. |
Fabrication of Pressure Parts of High-Pressure Boiler Components i.e. Water Wall Tubes, Economiser, LTSH, Loose Tubes, Panels, Roof Tubes. | RATANGARH/ ISGEC | 2.5 Years | Completed |
ICS Senegal
| Sr. No | Description of Works | Plant / Client Name | Duration | Status |
| 1 | Turn around Maintenance of SAP & PAP at 01 MT capacity at ICS-Senegal (International). Includes Piping, Equipment’s(rotary +Static) | ICS Senegal | 06 Month | Completed |